The Education Authority require additional teaching space for Colaiste Feirste school to accommodate 120 students. this 120m2 offsite project consisted of 16 CTX Plusline modules, creating 4 temporary classroom accommodation.
This offiste project began in August and finished for the start of the new school year.
A turnkey finish was then prepared, working closely with the EA to ensure a smooth handover for September.
P McVey Building Systems was appointed the main contractor by the EA for this project working alongside the Department of Education, to provide an offsite solution. The new accommodation would provide a safe working environment for all the students attending the Colaiste Feirste school.
Facility
The Plusline units made up a total of 4no 55m2 classsrooms
Project Overview
The 16 CTX modules were manufactured offsite with our plug and play system, meaning only a matter of a week for connections on-site.
Our team worked successfully to complete the additional teaching space accommodation to avoid disrupting the start of the new school year.
Timescale
The 120m2 CTX module additional space was manufactured and installed within 4 weeks from order. The strict program ensured the deadline was met on-time for the upcoming school year and before the pupils returned to school